Bathroom Remodel Order of Operations, From Demo to Final Caulk

A three-panel illustration shows the installation of a shower. A plumber in a dark green shirt works on copper pipes, then checks a tiled shower stall. Finally, a woman in a grey sweater turns on the shower head in a completed, white-tiled stall, causing water to spray down.

A bathroom gets built from the inside of the walls out. Pipes and wires go in first, then the waterproofing, then the tile, and the things you’ll actually touch every day go in last.

Here’s the bathroom remodel order of operations most jobs follow:

  1. Plan, pull the permit and order the slow items.
  2. Protect the house and shut off the water.
  3. Demolition.
  4. Subfloor and framing repairs.
  5. Rough plumbing, rough electrical and the exhaust fan.
  6. The rough inspection, with the walls still open.
  7. Insulation, cement board and drywall.
  8. Waterproofing and a water test of the shower.
  9. Prime and paint.
  10. Floor tile, then wall tile, then grout.
  11. Vanity, toilet and plumbing fixtures.
  12. Lights, switches and the fan cover.
  13. Glass door, accessories and caulk.
  14. The final inspection.

And at one point in the middle, the whole job stops and waits for someone who isn’t on the crew.

Before Demo: Plan, Permit and Order

You’ll do the first step before anyone swings a hammer. Pick the fixtures (at least their model numbers), get the permit moving and order anything with a long lead time. The order won’t hold if the parts don’t show up when their turn comes.

The shower valve, the tub or shower pan, the toilet and the vanity need to be chosen before rough in, since the plumber sets pipes to their specs. Our step by step guide to planning a bathroom remodel covers those decisions in the order they need to be made.


Steps 2 and 3: Protect the House, Then Demolish in Order

Before demo, the crew shuts off the water to the bathroom, caps the lines and covers the floors and doorways the debris will pass through. In Wilkes-Barre, a dumpster on the street needs its own city permit ($34.50 for five days, or $30 when it’s added to a building permit, per the city’s April 2025 fee schedule).

Demolition itself has an order too:

  • Fixtures first: toilet, vanity, mirror, lights and accessories.
  • Walls next: tile, backer board or plaster, and the tub or shower if it’s going.
  • Floor last: tile and underlayment, so the walls’ debris doesn’t land on a floor you’re keeping.

In a house built before 1978, painted surfaces may hold lead, and EPA rules require a certified renovator for paid work that disturbs more than a small area of them.


Step 4: Fix the Subfloor and Framing

With everything open, the crew can see what’s been hidden. Soft or dark subfloor around the toilet and under the tub gets cut out and replaced. Rotted studs, joists that were notched too deep by an earlier plumber and walls that aren’t plumb all get fixed now.

Any framing changes happen here too: a moved wall, a new niche between the studs, blocking for grab bars or a heavy vanity. It’s the cheapest moment in the whole job to do it.


Step 5: Rough Plumbing, Rough Electrical and the Fan

It’s the part of the job you’ll never see again once it’s done.

Rough plumbing comes first, because pipes can’t bend around things the way wires can. The plumber runs or reroutes the drains and vents, sets the toilet flange, runs the supply lines and mounts the shower valve body in the wall at the right depth and height. The plumbing code requires that valve to be a pressure balancing or thermostatic type, which keeps the shower from going scalding hot when someone flushes.

Rough electrical follows: new circuits, the boxes for lights, switches and outlets, and the GFCI protection that recent editions of the electrical code require in bathrooms. Your local permit office and a licensed electrician will confirm exactly which code edition your town enforces.

The exhaust fan goes in now as well, with a duct that ends outside the house. You’ll find fans blowing into the attic in plenty of older houses. The code doesn’t allow it, and the damp air it dumps up there can rot the roof framing over time.

The step after the walls close decides whether the shower leaks, and none of it shows once the tile is up.


Step 6: The Rough Inspection, With the Walls Still Open

Here’s where the job stops and waits. When the plumbing and wiring are roughed in, the building inspector comes to look at them while every pipe, vent, box and wire is still visible. Nothing gets covered until that inspection passes, and that’s true even when the crew’s ready to go.

So plan around it. The inspection is a fixed point in the schedule, not a formality. If the walls get closed first, the inspector can ask to have them opened, and the drywall or cement board gets torn out and paid for twice. Depending on your town, plumbing and electrical may be inspected on the same day or on separate visits, so ask when the permit is issued.

Rules vary by municipality, so our guide to bathroom remodel permits in Pennsylvania explains who needs a permit and what the inspector checks.


Steps 7 and 8: Close the Walls and Waterproof the Shower

Once the rough inspection passes, the walls close in this order:

  1. Insulation in exterior walls, so the new pipes there are protected from cold.
  2. Backer board in the shower and around the tub: cement board, foam board or a glass mat gypsum panel made for wet areas. Ordinary drywall and old greenboard don’t belong behind shower tile.
  3. Drywall on the rest of the room, then tape and mud.

Then comes the step that decides whether the shower leaks: waterproofing. Cement board on its own isn’t waterproof, so the shower gets a membrane over it, either a liquid one rolled on in coats or a sheet membrane bonded to the board, sealed at every seam, corner and pipe.

The shower pan gets a water test before any tile goes on. The drain is plugged, the pan is filled with about 2 inches of water and it’s checked for leaks. The plumbing code’s minimum test is short, but many installers leave the water in overnight, because a leak found now costs a roll of membrane and a leak found later costs the tile.


Step 9: Prime and Paint

Most crews prime and paint the ceiling and walls before the floor tile, vanity and toilet go in. There’s nothing in the way yet, and drips land on a floor that’s about to be covered.

Touch ups come last. A final coat or a few dabs go on at the very end, after the fixtures are in. Use a paint made for bathrooms, since steam is hard on flat wall paint.


Step 10: Tile, Floor Then Walls, Then Grout

Floor tile usually goes down before wall tile, so the wall tile can sit on top of it and the joint at the bottom stays tight. Some layouts reverse it (a shower floor set after its walls, for example), and your tile setter will follow the layout.

The shower floor is sloped toward the drain, and the walls are tiled up from it. Grout goes in once the tile has set, and it’ll need time to cure before anything else touches it.

Where tile meets the tub and in the inside corners, the joint gets caulk instead of grout. Those joints move a little as the house moves. Grout doesn’t flex, so it cracks there.


Steps 11 and 12: Fixtures, Then the Finish Electrical

With the tile done, the fixtures go in:

  • Vanity and top, then the faucet and the drain.
  • Toilet, set on its new flange after the floor is finished, so it seals at the right height.
  • Shower trim, the handle and plate on the valve that’s been in the wall since rough in, plus the showerhead.

Then the electrician comes back for the finish work: light fixtures, switches, outlets, the outlet covers and the fan’s grille.


Step 13: Glass, Accessories and the Final Caulk

A custom glass shower door is measured after the tile is finished, because the glass has to fit the walls as they actually ended up. Then it’s made, which one contractor’s 2026 survey of suppliers put at about 2 to 4 weeks. That’s why many bathrooms get used for a while with the door still missing.

Mirrors, towel bars, the toilet paper holder and any shelves go up next. Then a last bead of silicone caulk goes along the tub, the shower floor and the vanity top, and the painter does the touch ups.


Step 14: The Final Inspection

When the work is complete, the inspector comes back for the final. That usually means the fixtures work, the GFCI outlets trip and reset, the fan vents outside and nothing’s left open. Once it passes, you’re done with the permit.

For a small bathroom with no plumbing moves, Angi puts the whole sequence at about 3 to 4 weeks of work, and two to three months for a full remodel. How long a bathroom remodel takes breaks that time down week by week, and the order of operations for a whole house remodel covers how a bathroom fits in when other rooms are being done too.


How to Keep the Bathroom Remodel Order of Operations on Track

If you’re hiring a contractor, ask for the schedule in this order, with the rough inspection and the glass measurement marked as dates. If you’re coordinating trades yourself, book them in this order. Leave a cushion after the inspection, and hold to these four rules:

  1. Don’t let anyone close a wall before the rough inspection passes.
  2. Don’t let tile go on until the shower pan has passed a water test.
  3. Don’t set the toilet before the floor is done.
  4. Don’t order the glass until the tile is finished.

If you’d rather have one team run the whole sequence, 570 Remodeling can schedule each trade and inspection, and walk you through the plan before demo day.


FAQ

What is the correct order to remodel a bathroom?

Plan and order materials, demolish, then repair the subfloor and framing. Rough in the plumbing and wiring and pass the rough inspection before the walls close. Then waterproof the shower, paint, tile, install the fixtures and finish electrical, and end with the glass, caulk and the final inspection.

What should be done first in a bathroom remodel?

Picking the fixtures and pulling the permit come first, before demolition. The plumber needs the exact valve, tub or pan, toilet and vanity to set the pipes, and the permit has to be in place before rough work starts.

Do you paint a bathroom before or after tile?

Usually before the floor tile and fixtures go in, with touch ups at the end. Painting first keeps drips off finished surfaces and leaves nothing in the way.

Does flooring go in before the vanity or after?

In most bathrooms the floor goes in first and the vanity sits on top of it. That way a future vanity of a different size won’t expose bare subfloor.

Who do I hire for each part of a bathroom remodel?

A plumber for the drains, supply lines and valve, an electrician for the wiring, fan and lights, a tile setter for the backer, waterproofing and tile, and a carpenter or general contractor for demolition, framing and fixtures. A general contractor can schedule them all in order.

What is the hardest part of a bathroom remodel?

For most people it’s the waiting: the inspection, the tile curing and the custom glass. In terms of skill, the shower’s waterproofing and tile are the hardest to get right, because mistakes there show up as leaks years later.

Get Your Free Quote

Tell us about your project and we will get back to you with a real number for your space. No pressure, no obligation.

Free Quote (Footer)

Ready to Transform Your Home?

Our Wilkes-Barre team is ready to bring your vision to life. Get a free, no-obligation estimate today.

Written by the 570 Remodeling Team

570 Remodeling is Wilkes-Barre’s trusted local remodeling contractor, serving Luzerne County homeowners with bathroom, kitchen, basement, deck, siding, and roofing projects since day one. Every article is written from real field experience, not guesswork.

You Might Also Like

Ready to Start Your Remodel?

Wilkes-Barre’s local remodeling contractor, honest estimates, no pressure, real craftsmanship. Call us today or request your free quote online.