Demo day is easy to put on a calendar. Having every box the crew needs sitting in your garage before the old tile comes down is the hard part.
So here’s the bathroom remodel checklist in short. Before demo, decide the scope and layout, the tub or shower model, the shower valve and trim, the vanity and the toilet, the wiring and fan, the tile (with extra), the niche, and the type of shower glass. They’re the things the plumber and electrician need when the walls are open, or the things that take weeks to arrive. Paint, mirrors and towel bars can wait.
And the last thing installed in a new shower is one of the first things that has to be decided.
| Decision | Why it can’t wait | When the crew needs it |
|---|---|---|
| Scope and layout | Decides what gets torn out and whether pipes move | Before demo |
| Tub or shower model | Sets the drain spot, the wall framing and the alcove size | At rough in |
| Shower valve and trim | The valve goes in the wall long before you see the handle | At rough in |
| Shower glass type | Sets the curb and the wood blocking for the hinges | At rough in, then measured after tile |
| Niche size and spot | It’s framed into the wall | At rough in |
| Vanity and sink | Sets the drain and water line heights; custom ones take weeks | At rough in |
| Toilet | Has to match the drain distance from the wall | At rough in |
| Lights, outlets and fan | Wired while the walls are open | At rough in |
| Tile, with extra | Special orders take weeks, and a reorder can come from a different batch | Before waterproofing is done |
| Paint, mirror, hardware | Nothing behind the wall depends on them | After the walls close |
Why the Bathroom Remodel Checklist Runs on the Crew’s Schedule
Most checklists run in the order you’ll think about things: inspiration, budget, style. A crew works in a different order. Pipes and wires go in first, then the walls close, then tile, then fixtures. Anything the rough in depends on has to be settled before demo, even if you won’t see it for weeks.
The other clock is shipping. Block Renovation’s 2026 materials guide warns that special order vanities, custom or imported tile and glass shower enclosures can take weeks to arrive. Its example is a vanity that ships two weeks after demo, which leaves a crew with nothing to do. Its advice is to have everything on site or scheduled for delivery before demolition begins.
If you’re still setting goals and a budget, our step by step guide to planning a bathroom remodel comes first, and the general remodel planning checklist for the first 30 days covers contracts, permits and scheduling for any room.
Decisions the Plumber Needs at Rough In
These are the ones that get locked inside the walls and floor.
- Whether anything moves: moving a toilet or a shower drain changes the plumbing under the floor, so it’s decided before demo, not during it.
- The tub or shower base, by model: A tub’s drain side (left or right), its length and its height decide where the drain goes and how the wall is framed. A shower pan or tray does the same.
- The shower valve and its trim: The valve body sits in the wall, and the trim you pick later has to come from the same brand and usually the same valve line. So pick the handle style now. The plumbing code calls for a pressure balancing or thermostatic valve that guards against scalding, so ask which one you’re getting.
- The vanity, by model: Its height, depth and sink type set where the drain and water lines come out of the wall. A vessel sink or a wall hung vanity needs different heights than a standard cabinet.
- The toilet: it has to match the rough in distance, the gap from the finished wall to the center of the drain. That’s usually 12 inches, though older houses sometimes have 10 or 14.
Plan the spacing with the fixtures you’ve chosen, too. The code most towns use calls for at least 15 inches from the center of the toilet to a side wall or vanity, and 21 inches of clear floor in front of it.
Decisions the Electrician Needs While the Walls Are Open
Wiring’s cheap to change while the studs are bare, and it isn’t once they’re covered.
- Lights: where they go over the vanity, whether there’s one over the shower, and whether a dimmer makes sense.
- Outlets: how many, and where. Recent editions of the National Electrical Code require GFCI protection for bathroom outlets, and your electrician and the local permit office will confirm what applies to your job.
- The fan: its size, where it sits, and that it’s ducted to the outside, not into the attic.
- Anything heated: heated floor mats and towel warmers need their own wiring planned now.
Homeowners on Reddit’s home improvement forum (as rounded up by Apartment Therapy) keep giving one piece of advice here: put an outlet by the toilet even if you don’t want an electric bidet seat yet. Adding one later means opening a finished wall.
Decisions That Take the Longest to Arrive
These don’t go in the wall, but they’ll still hold up the job if they’re late.
The vanity: a stock vanity can often be picked up or shipped quickly. Semi custom and custom ones aren’t. A 2026 lead time tracker from a Phoenix remodeling firm that called a dozen suppliers put semi custom cabinets at about 4 to 8 weeks and fully custom at 8 to 12 weeks or more. Ask your supplier for a ship date before you sign.
Tile: special order and imported tile can take weeks, and a reorder restarts that wait. It can also come from a different production batch with a slightly different color.
Block Renovation suggests ordering 10 to 15 percent extra for standard tile in a simple layout, and up to 20 percent for mosaics or patterns. Buy it all at once.
The tub: a cast iron or freestanding tub is often a special order. And since its model sets the drain location, it has to be chosen before rough in, not just before install.
If keeping all of these choices straight sounds like a lot, a remodel mood board and selection sheet puts every model number, finish and order date on one page.
The Shower Glass: Installed Last, Decided First
Glass is the last big thing to go into a new shower. Dulles Glass, a shower door fabricator, says the final measurement can’t happen until the tile is finished and cured, and fabrication then takes about 8 to 10 business days.
But the type of glass has to be decided before demo. A heavy frameless door needs solid wood blocking inside the wall where the hinges will mount, and that blocking goes in while the studs are bare. The glass choice also shapes the curb the door closes against, and that curb is built long before the glass shows up.
So decide between a curtain, a framed door, a frameless door or a fixed panel now, and plan for about two weeks without a door between the tile and the glass.
The same blocking logic applies to grab bars. Even if you don’t want them yet, ask for blocking in the shower and beside the toilet. It costs very little with the walls open.
What Can Wait Until After Demo
Not everything has to be on the before list. These can be picked while the crew works:
- Paint color and finish
- The mirror or medicine cabinet (unless it’s recessed, which needs a framed opening)
- Towel bars, hooks and the toilet paper holder
- Cabinet hardware
- Bath mats, shower curtain and towels
One thing can’t be decided ahead at all: the condition of the subfloor and the framing. Ask for an allowance in the bid so rot or old damage has a price before anyone finds it. If you’re unsure how big the job really is, the difference between a refresh, a partial remodel and a full gut is worth settling first.
How to Use This Checklist Before Demo Day
- Two weeks or more before demo: confirm the scope, the layout and every fixture by model number, including the valve and trim.
- When you sign: get ship dates for the vanity, tile, tub and glass, and order anything special right away.
- Before demo: check that everything the rough in needs is on site, and open every box. A cracked tub or the wrong vanity is easier to fix now than mid job.
- Keep one sheet with every selection, quantity and delivery date, and give your contractor a copy.
When you’re weighing selections, a free estimate from 570 Remodeling is a good place to start: we’ll go through this list with you and flag which choices the crew needs first.
FAQ
What do you do first in a bathroom remodel?
Settle the scope and the layout, then choose the fixtures that set the plumbing: the tub or shower, the valve and trim, the vanity and the toilet. Those have to be decided before demo because the rough in plumbing is built around them.
Should I add an outlet by the toilet?
Usually yes, if the walls are open. It costs little during a remodel and lets you add an electric bidet seat later without opening a finished wall. It needs the same GFCI protection as the other bathroom outlets.
Can I buy my own materials for a bathroom remodel?
Often, but ask your contractor first. Many are fine with you buying finishes like tile, the vanity or fixtures, but they may not warranty materials they didn’t supply, and anything that arrives late or damaged delays the job.
How much extra tile should I order?
Plan on about 10 to 15 percent extra for standard tile in a simple layout and up to 20 percent for mosaics or patterns. Order it all in one batch so the color matches.
How long does a custom shower door take?
About two weeks after the final measurement, and that measurement can only happen once the tile is finished. A shower glass fabricator, Dulles Glass, puts fabrication at about 8 to 10 business days.
How do you choose a bathroom vanity size?
Measure the wall, then leave the clearances: at least 15 inches from the toilet’s center to the vanity and 21 inches of open floor in front of the toilet under the code most towns use. Check that the doors and drawers can open past the door swing and the toilet.