A bathroom remodel budget has about a dozen lines once the room is opened up. In the order the money gets spent:
- Demolition and disposal
- Permit and inspections
- Rough plumbing
- Waterproofing
- Tile labor and tile material
- Electrical
- Exhaust fan and ducting
- Drywall and paint
- Vanity and countertop
- Toilet
- Shower and sink trim (the handles, spout and showerhead)
- Contingency
Labor usually takes half or more of the total. Block Renovation puts it at 50 to 65 percent on a midrange bathroom, and Fixr’s national figure is about half.
The line most homemade budgets leave off sits behind the shower tile, and it often costs more than the tile does.
The Bathroom Remodel Budget, Line by Line
These ranges come from 2026 national cost guides, and they’ll swing with the size of the room, the finishes and local labor, so treat them as the shape of a budget, not a quote.
| Budget line | What it covers | Typical 2026 range | Source |
|---|---|---|---|
| Demolition and disposal | Tearing out tile, fixtures and drywall, plus the dumpster | $1,000 to $2,300 | Block Renovation, Angi |
| Permit and inspections | Building, plumbing and electrical permits where the town requires them | $100 to $1,000 | Block Renovation, Angi |
| Rough plumbing | New supply and drain work with fixtures staying in place | $3,000 to $5,000 | Block Renovation |
| Waterproofing and tile labor | Membrane and backer behind the shower, then setting the tile | $5,000 to $12,000 for a shower to the studs | Block Renovation |
| Tile material | Floor and wall tile | $2 to $40+ per square foot | Block Renovation |
| Electrical | New circuits, GFCI outlets, lighting | $800 to $2,500 | Block Renovation |
| Exhaust fan | A new fan with new ducting to the outside | $400 to $950 | Block Renovation |
| Paint | Walls and ceiling | About $1,145 on average | This Old House |
| Vanity | Cabinet and top | $400 to $700 budget; $1,200 to $2,500 midrange | Block Renovation |
| Toilet | Toilet and install | $200 to $400 budget; $530 to $710 midrange | Block Renovation |
| Shower trim | Handle, spout and showerhead | $80 to $150 budget; $400 to $500 midrange | Block Renovation |
| Contingency | Whatever turns up behind the walls | 10 to 20 percent of the total | Block Renovation, This Old House |
Two notes on reading it. Rough plumbing in that range assumes nothing moves. If you’re moving one fixture, Block Renovation adds $1,000 to $5,000. And it’s a tub to shower swap or a tiled shower that makes the waterproofing line big.
The Line Behind the Shower Tile
Waterproofing is the line that goes missing. It’s the membrane or coating and the backer board behind the tile, plus the labor to set the tile over it. Block Renovation prices the two together at $5,000 to $12,000 or more once a shower comes down to the studs.
Compare that with the tile itself. At $2 to $40 a square foot, the tile for a typical shower and floor often costs less than the labor and waterproofing underneath it, which is why a budget built from a tile store receipt comes up short.
It’s also the line you can’t see once the job’s done. A cheaper shower and a properly waterproofed one look the same on the day they’re finished, so it’s worth asking any contractor what goes behind the tile and getting it written on the estimate.
A Worked Bathroom Remodel Budget for a 5 by 8 Room
Added up for a full remodel of a 5 by 8 bathroom, with every fixture staying where it’s always been and midrange picks from the ranges above, it looks like this. Your numbers won’t match. What matters is the shape.
| Line | Amount |
|---|---|
| Demolition and disposal | $1,500 |
| Permit and inspections | $400 |
| Rough plumbing, fixtures in place | $4,000 |
| Waterproofing and tile labor | $7,000 |
| Tile material, about 120 square feet at $8 | $1,000 |
| Electrical | $1,200 |
| Exhaust fan with ducting | $600 |
| Paint | $1,145 |
| Vanity, midrange | $1,800 |
| Toilet, midrange | $600 |
| Shower trim, midrange | $450 |
| Subtotal | $19,695 |
| Contingency at 20 percent | $3,939 |
| Total to set aside | $23,634 |
Look at where it goes. The rough plumbing plus the waterproofing and tile labor come to $11,000, more than half the subtotal. The vanity, toilet and trim that people usually shop for first are about $2,850 of it.
That lines up with This Old House, which puts the average full remodel of a 40 to 150 square foot bathroom at $18,706. A plainer version of the same room can come in under $20,000 all in, and the line that moves most is the waterproofing and tile labor.
How the Budget Splits Between Labor and Materials
Most of a bathroom budget pays for labor. Block Renovation’s 2026 split for a midrange remodel is 50 to 65 percent labor, 30 to 45 percent materials, and 5 to 10 percent for permits, demolition and disposal.
Fixr slices it by part of the room instead:
- Shower or tub, about 25 percent
- Vanity and shelving, about 25 percent
- Fixtures, tile work and utilities (plumbing and electrical), about 10 percent each
- Countertops, about 6 percent
- Doors and windows, about 5 percent
- A cushion, about 5 percent
- Permits, about 4 percent
Those two views disagree a little, probably because Fixr’s $12,000 national average includes plenty of smaller jobs that keep the shower walls. Once the shower comes down to the studs, the labor share climbs toward Block’s numbers.
The same labor and materials logic runs through every room in the house, and our general guide to budgeting a home remodel line by line walks through it with a kitchen.
Lines Homemade Budgets Usually Miss
Most budgets people build themselves start at the vanity and work toward the tile, and that’s where these lines fall out:
- Disposal gets forgotten first. Old tile, a cast iron tub and drywall go somewhere, and a dumpster is part of the demolition line.
- Then there’s the permit. In Wilkes-Barre the city’s permit fee runs $59.50 to $224.50 for jobs under $10,000, climbs with the cost of the work above that, and adds a $60 residential inspection fee. Whether your bathroom needs one at all is covered in our guide to bathroom remodel permits in Pennsylvania.
- The fan’s duct is easy to miss. A new fan doesn’t cost much, but running a duct to the outside is what lands it at $400 to $950.
- Markup comes next. Block Renovation and Angi both put a general contractor’s fee at 10 to 20 percent. Some estimates show it as its own line and some fold it into each line.
- Contingency is the last. This Old House recommends 20 percent, and it’s the line that pays for rot under the toilet or an old drain that won’t hold.
How to Use This Budget With a Contractor’s Estimate
Build your own version of the list before anyone quotes the job. Then hold each estimate up against it, and you’ll spot the gaps fast. Missing lines are the tell. An estimate with no waterproofing line, no disposal or no permit usually grows once those get priced.
Ask each contractor to break the price into these same lines. Two bids that land $3,000 apart usually differ on one or two lines, and the line by line view shows you which. For the averages behind each number, see the full breakdown of bathroom remodel costs.
And if you’re still deciding what the room needs before you price it, start with the complete guide to remodeling a bathroom.
If you’re weighing options, 570 Remodeling’s free estimate starts with an on site visit and comes back as a detailed estimate covering materials and labor, which makes it easy to check against your own list.
FAQ
What percentage of a bathroom remodel budget goes to labor?
Usually half or more. Block Renovation puts labor at 50 to 65 percent of a midrange bathroom remodel, and Fixr’s national figure is about 50 percent, with a 40 to 65 percent range. Jobs that take the shower to the studs sit at the high end, because waterproofing and tile setting are mostly labor.
What is typically included in a contractor’s estimate for a bathroom?
A complete estimate lists demolition and disposal, permits, plumbing, waterproofing, tile labor and material, electrical, the fan, drywall and paint, the fixtures and trim, and the contractor’s fee, whether as one line or spread through the others. If a line is missing, ask whether it’s included or left for you to buy.
Is painting usually included in a bathroom remodel estimate?
Often, but it isn’t guaranteed. Some contractors include paint as part of drywall and finish work, and others leave it to the homeowner. This Old House puts painting at about $1,145 on average, so don’t assume it’s in there; confirm it in writing.
How do you estimate bathroom remodel costs before getting quotes?
List the lines above, mark which ones your job touches (a refresh skips demolition to the studs and most of the waterproofing), and put a low and high number beside each from published ranges. Add 10 to 20 percent for contingency. That gives you a range to hold each quote against.
How much contingency should a bathroom remodel budget have?
Between 10 and 20 percent of the total. This Old House recommends 20 percent, and older houses or bathrooms with signs of past leaks belong at the top of that range.